KOMPARASI BIAYA KONSTRUKSI BANGUNAN ATAS JEMBATAN SLAB ON FILE DI ATAS TANAH LUNAK UNTUK BEBERAPA VARIASI BENTANG Ruspiansyah, Ruspiansyah; Humaidi, Muhammad; Yanuar, Khairil
Jurnal Teknik Sipil Vol 4 No 2 (2020): Jurnal Gradasi Teknik Sipil - Desember 2020
Publisher : P3M Politeknik Negeri Banjarmasin

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31961/gradasi.v4i2.851

Abstract

Jembatan tipe slab on pile umumnya terdiri dari dua bentang atau lebih. Sampai saat ini belum ada ketentuan atau pedoman terkait dengan panjang bentang terkecil dan terbesar. Dengan demikian penentuan panjang bentang jembatan slab on pile lebih kepada engineering judgment desainer dan/atau pemilik jembatan. Penelitian ini mencoba menentukan panjang bentang optimal yang dapat menghasilkan biaya konstruksi bangunan atas yang minimal dalam satuan rupiah per satuan luas jembatan slab on pile di daerah tanah lunak. Adapun lokasi penelitian berada di Jembatan Ray 2 Kabupaten Barito Kuala. Dalam penelitian ini, jembatan dibagi kedalam tiga tipe, yaitu Tipe I dengan bentang segmental 4 m dengan banyak bentang lima bentang dan panjang bentang total 20 m, Tipe II dengan bentang segmental 5 m dengan banyak bentang empat bentang dan panjang bentang total 20 m, dan Tipe III dengan bentang segmental 7 m dengan banyak bentang tiga bentang dan panjang bentang total 21 m. Berdasarkan hasil desain, biaya konstruksi bangunan atas per satuan luas untuk untuk jembatan slab on pile tipe I sebesar Rp5,795,673.4, jembatan slab on pile tipe II sebesar Rp5,313,707.8, dan jembatan slab on pile tipe III sebesar Rp4,925,033.0. Perbedaan biaya konstruksi ini dipengaruhi oleh jumlah pier head yang dimiliki jembatan, dimana tipe III memiliki jumlah pier head terkecil Abstract Slab on pile bridges consist of two spans or more. Until now, there are not codes state cleary about shortest and largest span of slab on pile bridge. Therefore, decision about length of span tends to engineering judgement of designer and/or owner of the bridge. This research tries to propose about optimal span that obtain a minimal construction cost of superstructure of slab on pile bridge on soft soil area in rupiah per square area. This research is located at Ray 2 Bridge in Barito Kuala District. In this research, bridge classifies in three types: type I (4 m segmental length, 5 spans, and 20 m total span length), type II (5 m segmental length, 4 spans, and 20 m total span length), and type III (7 m segmental length, 3 spans, and 21 m total span length). According to design results in this research, construction cost of superstructure for type I, II, and III are Rp5,795,673.4, Rp5,313,707.8, and Rp4,925,033.0. construction cos differs among types because the numbers of pier head, wherein type III has smallest number of pier head
PERBANDINGAN BIAYA DAN WAKTU PEKERJAAN DRAINASE ANTARA METODE PRECAST DAN CAST IN SITU Maryanto, Adi; Ruspiansyah
Jurnal Teknik Sipil Vol 5 No 1 (2021): Jurnal Gradasi Teknik Sipil - Juni 2021
Publisher : P3M Politeknik Negeri Banjarmasin

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31961/gradasi.v5i1.980

Abstract

Metode Precast dan metode Cast in Situ merupakan metode pekerjaan drainase dengan kelebihan dan kekurangan tersendiri. Pelaksanaan Metode Precast dan Cast in Situ pada pekerjaan drainase belum bisa dikatakan tepat, sehingga perlu dilakukan analisa perbandingan mengenai biaya dan waktu pekerjaan. Tujuan dari penelitian ini untuk mengetahui seberapa besar efisiennya kedua metode tersebut. Metode penelitian yang digunakan ialah dengan perbandingan hasil antara metode Precast dan metode Cast in Situ. Data yang diolah berupa data sekunder yang didapat dari kontraktor pelaksana. Untuk penyusunan penelitian ini meliputi studi pustaka atau literatur, pengumpulan data, perhitungan volume, metode pelaksanaan dan analisa harga satuan dan biaya. Lokasi studi berada di PLTU Suralaya Banten. Berdasarkan perhitungan volume, analisa harga satuan pekerjaan, rencana anggaran biaya, analisa produktifitas pekerjaan diperoleh hasil untuk biaya metode Cast in Situ sebesar Rp 5.543.804.100,00 dan biaya metode Precast sebesar Rp 3.994.718.900,00. Waktu pekerjaan menggunakan metode Cast in Situ memerlukan waktu 116 hari sedangkan untuk waktu pekerjaan metode Precast selama 29 hari. Jumlah pekerja metode Cast in Situ sebanyak 64 pekerja dan metode Precast sebanyak 17 orang. Berdasarkan hasil analisa dapat disimpulkan metode Precast ialah metode yang paling efisien digunakan.