Penerapan Metode Earned Value Analysis Terhadap Waktu Penjadwalan: Studi Kasus: Pembangunan Gedung Ruang Kelas Baru (RKB) Pada Madrasah Aliyah Negeri (MAN) Kab. Karawang

Syapril Janizar (Unknown)



Article Info

Publish Date
31 May 2023

Abstract

Project management is an activity which consists of planning, leading, organizing, and controlling the company's organizational resources to achieve predetermined organizational goals within a certain period of time with certain resources. Case study on the Project for the Construction of a New Classroom Building (RKB) for the State Madrasah Aliyah (MAN) Kab. Karawang which is located Karawang, West Java 41314. Analyzing the project using the concept of Earned Value Analysis which is focused on the implementation of the Project for the Construction of a New Classroom Building (RKB) of the State Madrasah Aliyah (MAN) Kab. Karawang. Knowing and adding insight about cost and time control on a project by applying Earned Value Analysis. The work completion time is in accordance with the work plan so that the work can be completed according to schedule.

Copyrights © 2023






Journal Info

Abbrev

konstruksi

Publisher

Subject

Civil Engineering, Building, Construction & Architecture

Description

Jurnal Kosntruksi yang dapat menampung dan mempublikasikan hasil karya penelitian, karya tulis dan pengabdian masyarakat baik mahasiswa dan dosen-dosen intern maupun dari pihak luar. Jurnal Konstruksi memberikan informasi yang diperoleh dari laboratorium dan workshop penelitian maupun dari lapangan/ ...