Repair Project Acceleration Strategy of Three Ship Units using Fuzzy Logic Analysis and Critical Path Method

Hidayatus Ubyani (Department of Naval Architecture, Universitas Diponegoro, Semarang 50275, Indonesia)
Tuswan Tuswan (Universitas Diponegoro)
Hartono Yudo (Department of Naval Architecture, Universitas Diponegoro, Semarang 50275, Indonesia)
Haris Nubli (Department of Marine Convergence Design Engineering, Pukyong National University, Busan, 48513, South Korea)
Ocid Mursid (Department of Naval Architecture, Universitas Diponegoro, Semarang 50275, Indonesia)
Muhammad Iqbal (Department of Naval Architecture, Ocean and Marine Engineering, Henry Dyer Building, University of Strathclyde, Glasgow, UK)



Article Info

Publish Date
05 Oct 2023

Abstract

The project planning process, especially in ship repair projects, is essential to improving project completion. Ineffective planning of ship repair projects results in a lack of time and labour efficiency. Therefore, using project acceleration tools in scheduling ship repair activities is crucial to accelerate project completion and mitigate risk analysis of delays for each project activity. This research uses the critical path method (CPM) to analyze the main schedule of three combined ship repair projects. Then, shop-level planning is used to determine the productivity of each workshop so that each workshop knows the volume of work that needs to be completed daily. Furthermore, fuzzy logic is applied to analyze the risk of delays in repair project activities. The addition of working hours to critical work activities is accelerated from 30 days, the normal duration, to 23 days. Meanwhile, the addition of the workforce to critical work activities is accelerated from 30 days, the normal duration, to 22 days. The analysis of productivity values in each workshop results in the following productivity values: sandblasting and painting workshop 309.97 m2/person-days, piping workshop 4.12 units/person-days, fabrication workshop 407.16 kg/person-days, outfitting workshop 14.8 units/person-days, tank cleaning workshop 114.36 m3/person-days, and machining workshop 2.7 units/person-days. The fuzzy logic analysis results to determine the risk of delays in critical activities show that jobs with the codes SP1, SP2, SP3, SP4, M2, and SP5 have a high risk of delay. Additionally, the collaboration with other departments in the company, such as the marketing, finance, and human resources departments, is ongoing to complete assigned tasks.

Copyrights © 2023






Journal Info

Abbrev

mekanika

Publisher

Subject

Description

"Mekanika: Majalah Ilmiah Mekanika" is an open-access journal published by Mechanical Engineering Study Program, Faculty of Engineering, Universitas Sebelas Maret. Mekanika invites scholars, researchers and practioners who have interest in mechanical engineering to publish their articles and also ...