Standarisasi Kinerja Waktu dan Biaya dengan Metode Earned Value pada Tahap Pekerjaan Struktur Proyek

Andre Agitiya Wahyu (Universitas Muhammadiyah Jember)
Amri Gunasti (Universitas Muhammadiyah Jember)
Ilanka Cahya Dewi (Universitas Muhammadiyah Jember)



Article Info

Publish Date
16 Jan 2024

Abstract

The Jember Millennium Home Center Project experienced delays, because there was a difference between the costs that should have been spent not in accordance with the scheduled work performance and the difference here is negative. Therefore, research on cost index analysis and schedule performance index on the Jember Millennium Home Center project has no shortage of costs and the realization of completion work in the field is late. The purpose of this research is to calculate CPI and SPI. The method used in this research is Earned Value Analysis. The results showed that the Schedule Variant (SV) had a negative value of -Rp.30,940,091.57. While the value (CV) for 15 weeks has a positive value of Rp. 16,779,031.46, - from the difference in BCWP fees of Rp. 47,719,123 and ACWP Rp. 30,940,091, - means the project does not suffer losses.

Copyrights © 2024






Journal Info

Abbrev

civilengineering

Publisher

Subject

Civil Engineering, Building, Construction & Architecture Engineering

Description

Sustainable Civil Building Management and Engineering Journal is an academic journal organized which a focus and scope: Sustainable Building Design and Construction, Civil Engineering for Sustainability, Building Management and Maintenance, Environmental and Social Considerations. The scope of ...