Claim Missing Document
Check
Articles

Found 2 Documents
Search
Journal : Jurnal Teknik Industri Terintegrasi (JUTIN)

Optimasi Durasi Proyek dengan Penambahan Tenaga Kerja dan Jam Kerja Metode What If pada Proyek Pembangunan Gedung Soetandyo Universitas Airlangga Arifa Mardiah; Hanie Teki Tjendani
Jurnal Teknik Industri Terintegrasi (JUTIN) Vol. 7 No. 2 (2024): April
Publisher : LPPM Universitas Pahlawan Tuanku Tambusai

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31004/jutin.v7i2.29356

Abstract

Project delay is one of the impacts of decreased performance, and this can result in schedule setbacks and other forms of losses that will be experienced by service providers and service users. The purpose of this research is to find the optimum duration in accelerating the duration for delays of 10%-40%. In the Airlangga University Soetandyo Building Construction Project, there was a deviation in field realization progress of -9.210% and the cause of the initial delay was deep foundation work. What if is one method or strategy that can help project delay management by adding workers and increasing working hours on jobs in the critical path that are experiencing delays. As for the 10% delay, 78 additional workers and 19 additional working hours were obtained, for the 20% delay, 223 additional workers and 25 additional working hours were obtained, and for the 30% delay, 205 additional workers and 39 additional working hours were obtained
Analisis Tingkat Risiko pada Proyek Pembangunan Perumahan Grand Eastern Surabaya dengan Metode Severity Index Daniswara Fawwaz Febryan; Hanie Teki Tjendani
Jurnal Teknik Industri Terintegrasi (JUTIN) Vol. 7 No. 2 (2024): April
Publisher : LPPM Universitas Pahlawan Tuanku Tambusai

Show Abstract | Download Original | Original Source | Check in Google Scholar | DOI: 10.31004/jutin.v7i2.29772

Abstract

The Grand Eastern Surabaya housing development project is one of the housing projects owned by East Park Regensi which is the second stage of development of the Eastern Park Residence housing. The study aims to identify risks relevant to the Grand Eastern Surabaya housing construction project. The study used validity tests and reliability tests with the help of IBM SPSS software to determine the suitability of risk variables and to know the consistency of the risk variable in the Grand Eastern Surabaya housing construction project. Using the severity index and the probability impact matrix methods, it was found that there are 2 risks with very low categories, 10 risks in low Categories, 4 risks for medium categories and 6 risks of high categories.