Evaluasi Pelaksanaan Proyek Drainase Dengan Metode CPM Dan PERT

Gunaedy Utomo (Universitas Balikpapan)
Irna Hendriyani (Universitas Balikpapan)
Siti Nor Aida (Universitas Balikpapan)



Article Info

Publish Date
01 Dec 2020

Abstract

This research purposes to evaluate the implementation of the drainage project in Jl. Mulawarman, Gg. Arjuna, Sepinggan. This research uses the CPM (Critical Path Method) and the PERT (Project Evaluation and Review Technique). Based on the budget plan, time schedule, weekly report, documentation and interview found that the result of the CPM with two critical paths are work activities. The first critical path are: Activity A (Mobilization and Demobilization), Activity C (Landfilling activity), Activity F (Concrete works K-175, Ready Mix). The second critical path are: Activity A (Mobilization and Demobilization), Activity E (Begisting work for black channels), and Activity G (Plain U24 Concrete Iron Works). Meanwhile, the result of PERT has 49% chance to be completed with the project duration of 18 weeks.

Copyrights © 2020






Journal Info

Abbrev

mits

Publisher

Subject

Civil Engineering, Building, Construction & Architecture

Description

The publication of Media Ilmiah Teknik Sipil certainly participates in disseminating the results of research and review of science and technology development conducted by lecturers and researchers especially from UM Palangkaraya and other universities. This edition contains 8 articles consisting of ...