ANALISIS PERCEPATAN PROYEK DENGAN METODE CRASHING PROGRAM PADA PROYEK PEMBANGUNAN GEDUNG RUMAH SAKIT ISLAM UNISMA MALANG: Studi Kasus : Pembangunan Gedung Rumah Sakit Islam Unisma Malang

Widia Pertiwi (Teknik Sipil S1, Insititut Teknologi Nasional Malang)
Maranatha Wijayaningtyas (Unknown)
Tiong Iskandar (Teknik Sipil S1, Institut Teknologi Nasional Malang)



Article Info

Publish Date
02 Jun 2023

Abstract

The implementation of the Unisma Malang Hospital Building Construction with a completion time of 364 days, starting on March 1, 2020 and targeted for completion on August 12, 2021, but experiencing delays in its implementation.The acceleration is carried out using the Crashing Program method with alternatives that can reduce project time. The data used to conduct this research is secondary data in the form of budget plan data, time schedule, plan drawings. Analysis of the calculation of the acceleration of time with the addition of working hours (overtime) with a reduced duration of 5 days with an additional cost of Rp. 57.326.997.730,48,while with the addition of labor it is reduced by 10 days with an additional cost of biaya Rp 57.311.987.522,00, of the normal cost. So the results with the optimum crash is the addition of workers.

Copyrights © 2023






Journal Info

Abbrev

gelagar

Publisher

Subject

Civil Engineering, Building, Construction & Architecture

Description

Gelagar merupakan e-journal yang dikelola oleh Program Studi Teknik Sipil S-1 ITN Malang untuk menyebarluaskan informasi hasil - hasil penelitian mahasiswa dalam bidang Teknik Sipil dengan Sub bidang Struktur, Geoteknik, Transportasi, Manajemen Konstruksi, Sumber Daya Air dan Sistem Informasi ...